Subcontract Number: P11-1256/NSCC-PMT/SUBCON-0014
FW was responsible for the provision of all necessary labor,
material, equipment, mobilization, demobilization and
supervision to carry out the subcontract works as per contract specification, drawings, bill of quantities for the Construction of Siphon of Shatt Al Arab and Appurtenant Structures at Chelamcha and Abu Flooss area in Basrah, Iraq

Client: NSCC International Limited Country: Iraq
Contract Duration: 12 Months
Date of
Commencement: 19th January 2012
Date of Completion: 17th January 2013