Inspection, Cleaning and Repair of Crude Oil Storage Tanks.

FW was responsible for Cleaning, inspection, repairing, Painting Testing and do the Hydro Test for Two Storage Tanks for Crude Oil.

Client: Tadbir Energy Gostar Iranian Company (TEGIC) Country: Iraq, Basrah
Contract Duration: 6 Month
Date of
Commencement: May 2014
Date of Completion: October 2014

32” X42 Km Natural Gas Pipeline Project of Sharhraban/Diyallah

Contract Number: ICG-T/3/174
The scope of work includes design, supply, installation/
erection, testing & successful commissioning and handing over to ICG Group/SOC the complete Gas Pipeline Work on item rate contract.

Client: ICG Group, Pipelines Special Services
Country: Iraq
Contract Duration: 12 Months
Date of
Commencement: 25th May 2015
Date of Completion: 24th May 2016

Executing all the works for the Operation of construction and installation of the G.R.S station of Abadan -Basra 48” Gas Pipeline Project (shat Al Basra G.R.S).

Contract NO.:-TEGI.Co./AB/C2/2018 .
The scope of work includes construction , installation and
handing over to Tadbir Energy Gostar Iranian Company (TEGIC) of gas reciever station (G.R.S).

Client: Tadbir Energy Gostar Iranian Company (TEGIC)
Country: Iraq
Contract Duration: 4 Months
Date of
Commencement: 1 Jan 2018
Date of Completion: 1 April 2018

48”X10 Km Natural Gas Pipeline Project of Balad Rooz/ Diyallah

Contract Number: ICG-T/3/174
The scope of work includes design, supply, installation/
erection, testing & successful commissioning and handing over to ICG Group/SOC the complete Gas Pipeline Work on item rate contract.

Client: ICG Group, Pipelines Special Services
Country: Iraq
Contract Duration: 5 Months
Date of
Commencement: 5th October 2013
Date of Completion: 12th March 2014

48”X17 Km Natural Gas Pipeline Project of Nahrawan / Diyallah

Contract Number: ICG-T/3/316
The scope of work includes design, supply, installation/
erection, testing & successful commissioning and handing over to ICG Group/SOC the complete Gas Pipeline Work on item rate contract.

Client: ICG Group, Pipelines Special Services
Country: Iraq
Contract Duration: 5 Months
Date of
Commencement : 25th May 2015

Date of
Completion: 29th October 2015

Construction of Siphon of Shatt Al Arab and Appurtenant Structures

Subcontract Number: P11-1256/NSCC-PMT/SUBCON-0014
FW was responsible for the provision of all necessary labor,
material, equipment, mobilization, demobilization and
supervision to carry out the subcontract works as per contract specification, drawings, bill of quantities for the Construction of Siphon of Shatt Al Arab and Appurtenant Structures at Chelamcha and Abu Flooss area in Basrah, Iraq

Client: NSCC International Limited Country: Iraq
Contract Duration: 12 Months
Date of
Commencement: 19th January 2012
Date of Completion: 17th January 2013

Construction and Commissioning of Buzurgan Oil Export Pipeline Project.

Subcontract Number: DPABI/IR/JS-MS/2013-028
FW was responsible for the provision of construction and commissioning of Buzurgan Oil Export Pipeline Project in compliance with the requirement of DPABI. The work
includes procurement, fabrication, manufacture, transportation, handling, positioning, installation, maintenance and service.

Client : Daqing Petroleum Administrative Bureau Branch, Iraq (DPABI) Country: Iraq
Contract 96 days

Date of
Commencement: 10th December 2013
Date of Completion: 31st March 2014

New Intake Water Pump Station PCC

Contract Number: CMITWRS-781-PRT-10.53-30255-1
FW was responsible for survey, design (architectural,
structural), engineering and construction of New Intake Water Pump Station PCC.

Client: CNOOC Iraq Limited

Country: IRAQ

Contract Duration: 12 Months

Date of
Commencement: 10th August 2014

Date of Completion: 9th August 2015

Water Injection Stations

Contract Number: CMIT-PRT-10.30-180025
FW was responsible for ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) of Water Injection Stations
 Design and Engineering of
 Procurement
 Construction
 Mechanical Completion
 Commissioning Support
 Provisional Acceptance
 Warranty
 Final Acceptance
 Demobilization

Client: CNOOC Iraq Limited Country: Iraq
Contract Duration: 1.5 Years
Date of
Commencement: 7 Aug 2018
Date of Completion: 1 April 2020